Road Work Advisories

About Our Advisories

Online resources for up-to-date information about City of Eugene transportation system road construction. Read below for the weekly roadwork report (available April- November).


Current City of Eugene Roadwork Advisories

Updated July 1, 2022


Major road construction is scheduled for the week of July 4, weather permitting. Use caution in work zones and obey traffic control signage and flaggers. Links to additional project information can be found at www.eugene-or.gov/roadwork. For real-time traffic impacts, go to TripCheck.com or twitter.com/EugenePW. No work planned for July 4. Construction to resume July 5.


City of Eugene


17th Ave, 19th Ave & Mill St Paving –Striping will be occurring throughout the project limits. Traffic will be directed around the location of work being performed with minimal impacts. Please be mindful of construction crews and give them safe distance to work as you pass by.
 

Catalina St, Chase St, Concord St, Echo Hollow Rd, Fuller Ave & Hawthorne Ave Paving – striping will be occurring throughout the project limits. Traffic will be directed around the location of work being performed with minimal impacts. Please be mindful of construction crews and give them safe distance to work as you pass by.
 

Coburg Road (Ferry Street Bridge to Willamette River Bridge) - Day work on the Willamette River Bridge will continue with cleaning and structural work under the bridge. There will be no impacts to the public.
 

Downtown Wayfinding Signs - The City will be installing wayfinding signs throughout the downtown corridor. Construction crews will be minimal, and their work will be behind the curb. Little to no traffic disruption is anticipated. Please be mindful of construction crews and give them safe distance to work as you pass by.
 

Peter DeFazio Bridge – The bridge will be open and ready for use. The contractor will be some additional painting to complete in August. No delays or closures starting July 5th.

Bailey Hill Road, W. 5th Ave south to W. 18th Ave.: Crack seal crew will be working first on the section of 5th Ave to 11th Ave, then on 11th Ave to 18th Ave., on July 5th through 7th. Crew onsite from 7:00 to 3:00, watch for flaggers. Expect a small delay. All work is weather dependent.

E 13th Ave. between High Street and Mill Street: Road closed for asphalt repair on July 6th, crew onsite from 7:00 to 4:00.
 

W 11th Ave and Olive St.: July 7, one lane of W. 11th and northbound Olive Street between W. 11th and W. 12th closed for small asphalt repair.  Watch for cones to divert traffic away from repair location.  Impacts to m 12th St. to 11th Ave. The northbound turning lane on Olive to 11th will be open.
 

Jessen Dr, Clarey St & Robin Ave - Work is near completion on Jessen Dr between Elizabeth St and Hwy 99, on N Clarey St between Bean St and Century Dr, and on Robin Ave between Taney St and Ruskin St. Expect minor delays in the area as construction crews perform final landscaping work and small cleanup items.  Localized lane or sidewalk closures are possible in areas where some remaining work may be required. Use of alternate routes is encouraged when possible.  No work or closures will be in effect on Monday July 4 in observance of Independence Day.

 

Grand Cayman Dr (north of Barbados Dr) – Ongoing construction of Striker Field Park adjacent to Grand Cayman Dr will have limited impact on local traffic until the fall of 2022.  Please watch for the movement of workers, construction equipment and trucks.      
 
Silver Ln west of River Rd – Work is ongoing at North Eugene High School on the south side of Silver Ln through the summer to April 2023. Work includes pavement repair, walk, curb and gutter replacement. Potential flagging as required.  
 

Inlet Bottom Construction and Repairs – This project will clean and construct new catch basin/inlet bottoms in 212 structures throughout Eugene. Work will be occurring at multiple locations. This work will protect ground water quality and improve maintenance efficiency. Pedestrians should expect detours to be signed where sidewalks are disrupted. Use alternate routes when possible. Project is weather dependent and is expected to be completed no later than August 15th, 2022.

 

Gilham Road at Creekside Way – Crews will be on site working on excavating and installing storm sewer pipe on Creekside Way from Gilham Rd towards Sterling Woods Dr. and on Gilham Rd. from Mirror Pond Way to Heather Grove Ln. Expect road closures and limited on-street parking and driveway access. Use alternate routes when possible. 


Lane County
 

Coburg & Marcola

Chipseal surface treatments will be performed Tuesday through Thursday depending on weather and materials availability. Traffic will be controlled by flaggers. Expect delays and seek alternate routes whenever possible.

Coburg Road MP 7.40 – 12.88 (N. Coburg to Linn County)
Howard Road MP 0.00 – 1.48 (Marcola Rd to End County Maintenance)
Johnson Road MP 0.00 – 0.93 (Marcola Rd to End County Maintenance)
Old Marcola Road MP 0.00 – 0.60 (Entire Road)

Mohawk Loop Road MP 0.00 – 0.69 (Entire Road)

Mohawk River Road MP 0.00 – 2.16 (Marcola Rd to End County Maintenance)

Marcola Road MP 11.75 – 20.65 (North of Marcola to Linn County)


See all current ODOT Projects happening in Eugene.